Valve documentation: what to request before ordering

Understand the different roles of product drawings, material records, test reports and company certificates in a valve purchase.

Understand the different roles of product drawings, material records, test reports and company certificates in a valve purchase.

Different documents answer different questions

A company certificate, a product drawing and a test report are not interchangeable. A useful document package connects the supplier, the quoted configuration and the supplied valves to the requirements in your order.

Prepare a document register with a description, required issue stage and approval responsibility for every item. This is more actionable than requesting “all certificates” without defining the scope.

Identify the applicable design references

A design standard establishes requirements within its stated scope. For example, ASME describes B16.34 as covering areas including pressure-temperature ratings, materials, testing and marking for the valve constructions addressed by that standard.

Ask for the applicable standard and edition to be identified in the technical offer. A standard number on a website does not establish the compliance of a particular offered configuration or prove that the supplier holds a certification.

Use drawings to confirm the offered configuration

Request a drawing that corresponds to the quoted size, end connections and operator. Review installation dimensions, operating clearance and orientation before approval.

A generic catalogue image is useful for identifying a product family, but it does not replace a configuration-specific drawing. Keep the approved revision associated with the purchase order.

Link material and test records to the supplied items

Define the material and traceability records that the project requires. Agree how supplied valves or batches will be identified so that the supporting records can be matched to them.

For testing, specify the applicable procedure or standard, acceptance criteria, witness requirements and required report format. Do not assume that a reference to “tested valves” includes every test your project needs.

Verify the scope of company certificates

When certification is required, check the exact legal entity, covered location, scope, issuing body and validity. A certificate covering a different site or activity may not satisfy the procurement requirement.

Use the issuer’s verification process where available. For API-related requirements, distinguish the technical standard from the relevant licensing or certification programme and request the appropriate evidence.

Agree on the handover package before purchase

List required documents in the enquiry and confirm them in the order. Identify which records must be accepted before manufacture, shipment or final payment.

Vanta Valve’s verified company certificates and product reports have not yet been published in this preview. The documentation checklist is a procurement aid, not evidence of certifications held by Vanta Valve.

Reference sources

ASME — B16.34 scope API — Specification 6D

Put the guide to work

Standards & certificationsSupplier certification informationInclude documentation in your RFQ
Back to all articles
LET’S TALK SPECIFICATIONS

Your application.
Our next conversation.

Share your operating conditions, specifications and project requirements.

Request a Quote
VANTA VALVE / RESOURCES

How to compare industrial valve quotations

Look beyond the unit price. Compare technical deviations, testing, documentation and delivery scope before selecting a valve supplier.

Look beyond the unit price. Compare technical deviations, testing, documentation and delivery scope before selecting a valve supplier.

Put every quotation on the same basis

Two quotations for the same valve family may cover different configurations. Before comparing totals, create a line-by-line comparison using your original enquiry as the baseline.

Keep the supplier’s exact wording where a requirement is uncertain. Mark an unanswered item as “not confirmed”; do not treat a blank cell as acceptance.

Resolve technical differences first

Compare the offered size, pressure class, materials, seats, connections and operator with the required configuration. For every difference, record whether it is acceptable, needs engineering review or must be revised.

An alternative material or connection is not automatically equivalent. It can affect compatibility with the process or the installation. Request a written explanation and route it to the person responsible for the project specification.

  • Match each offered item to your enquiry line number.
  • Check body and trim grades separately.
  • Compare the complete operator and accessory scope.
  • Confirm the drawing dimensions and any site constraints.

Compare inspection and documentation scope

Testing and documents are part of the supply scope. One offer may include only the supplier’s normal documentation while another includes project-specific witness points and material records.

Use a document checklist to compare what will be supplied, when it will be issued and whether approval is required. Resolve missing inspection activities before evaluating the offers as equivalent.

Check delivery and commercial assumptions

Compare the delivery basis, packaging, freight, currency and payment milestones. Ask whether quoted lead time begins at order placement, payment or drawing approval.

For a staged project, identify whether partial shipments are permitted and whether documents must be approved before dispatch. These details can matter more to the installation schedule than a small unit-price difference.

Close the gaps before issuing the order

Create one clarification list for each supplier. When replies arrive, update the comparison and keep the supporting correspondence.

The accepted technical offer, agreed deviations, drawing revision and document list should be traceable to the purchase order. This creates a clearer basis for inspection and acceptance when the valves arrive.

Put the guide to work

RFQ checklistQuality control requirementsRequest a Quote
Back to all articles
LET’S TALK SPECIFICATIONS

Your application.
Our next conversation.

Share your operating conditions, specifications and project requirements.

Request a Quote
VANTA VALVE / RESOURCES

What to include in an industrial valve RFQ

A practical checklist for procurement teams: service conditions, valve specifications, documentation and the details that make quotations comparable.

A practical checklist for procurement teams: service conditions, valve specifications, documentation and the details that make quotations comparable.

Start with the duty, not just a product name

“Ball valve, four inch, ten pieces” can start a conversation, but it leaves several decisions open. A supplier still needs to understand what the valve must do, the fluid it will handle and the conditions it will experience.

Give each valve or group of identical valves a line-item number. Keep that number consistent across the enquiry, technical offer, drawing and purchase order. This makes it easier to identify changes when several configurations are being quoted.

  • Identify isolation, throttling, non-return or diversion duty.
  • State the installation location and available operating clearance.
  • Describe how frequently the valve operates and any special shutdown requirements.

Record the full operating conditions

Include the medium and its composition, normal operating pressure and temperature, and the project design conditions. Identify units explicitly. If the fluid contains solids or has a variable composition, explain those conditions rather than supplying only the fluid name.

Do not replace a missing value with a guess. Mark it as “to be confirmed” and identify who will supply it. This distinguishes an open engineering item from an agreed requirement.

Define the configuration line by line

Keep process requirements separate from the requested hardware configuration. The technical offer should confirm both. A clear enquiry allows a supplier to identify a conflict instead of silently substituting a different component.

  • Valve family, nominal size and bore requirement.
  • Pressure class or PN, together with the design conditions.
  • Body, trim, seat and sealing material requirements.
  • End connections, dimensions and flange requirements.
  • Manual, electric or pneumatic operation and available utilities.
  • Quantity for each configuration, including any spare parts.

Specify the documents you will actually need

List applicable standards and editions from the project specification. Separate a product design requirement from a manufacturer certification requirement: they answer different questions.

Include drawing approval, material records, inspection plans, test reports and any witness requirements in the original enquiry. Adding these after a purchase order may change the scope, schedule or price.

Make the commercial responses comparable

Ask the supplier to identify deviations and exclusions explicitly. Record what the offered price includes: operators, accessories, testing, documentation, packaging and freight can otherwise be interpreted differently.

Provide the delivery destination and required project date. Ask for the quoted delivery basis and the event that starts the lead-time calculation, such as drawing approval. These should be stated in the offer rather than assumed.

Send one consistent enquiry package

Combine a numbered valve list, project datasheets and relevant specifications. Give the package a revision number so that updated requirements do not get mixed with an earlier enquiry.

Before ordering, reconcile the accepted offer against that package. Close out technical deviations in writing and keep the final drawing and document list with the purchase record.

Put the guide to work

Prepare a valve RFQValve selection guideExplore ball valves
Back to all articles
LET’S TALK SPECIFICATIONS

Your application.
Our next conversation.

Share your operating conditions, specifications and project requirements.

Request a Quote